Back to Bhutan main page



Objectives and Strategies of the Eighth Five-Year Plan
  • Implement construction, selectively, of power projects for which detailed project reports have been completed;
  • Enhance revenue collection by efficient operation of the existing hydropower stations and distribution systems;
  • Encourage the use of energy like hydropower, which are renewable, environmentally clean and sustainable;
  • Expand rural electrification;
  • Liase with other Government agencies to ensure the protection of existing and future hydropower catchments areas; and
  • Develop policy guidelines and power tariffs conducive to the promotion of bilateral and multilateral cooperation in hydropower development
While most major programmes were centrally executed, the rural electrification programme was implemented at the Dzongkhag level with close coordination and cooperation of Dzongkhag authorities by the Dzongkhag based Electricity Supply Sections of the Department of Power. The beneficiaries (communities) were closely involved at the geog and village level during programme implementation.

The Power Generation Programme


Major projects for implementation during the 8FYP such as the Kurichu, Basochu and Tala hydroelectric projects were reflected outside the plan budget outlay. The Kurichu project of 60 MW and 400 MU generation capacity, construction of which started during the 7th Five Year Plan, was completed during the 8FYP and has started supplying electricity to six Dzongkhags in eastern Bhutan and two Dzongkhags in southern-central Bhutan.

Surplus energy (about 90 per cent) from Kurichu is being exported to the northeastern grid of India through the existing 132 kV Gelephu-Salakati power line. Implementation of the Kurichu project has facilitated other economic development activities in the eastern and south-central region of Bhutan. Basochu Upper Stage of 22.2 MW and 105 MU generation capacity was also completed and has augmented capacity in western Bhutan as well as increased the reliability of grid-supply in the capital.

The construction of the Tala hydroelectric project of 1020 MW started during the 8FYP, and more than 50 per cent of
the project has now been completed. Physical construction of the Basochu Lower Stage of 38.6 MW capacity has just started. Tala and Basochu Lower Stage will be completed during the 9th Five Year Plan (9FYP). Rongchu micro hydro of 200 kW capacity built across the Rongchu stream in Kellungchu valley of Lhuentse Dzongkhag has been completed. This pilot project was built under the Joint implementation Testing Programme, funded by the Environment Ministry of the Netherlands and the Government of Bhutan to test the possibility of sequestration of green house gases. This is the first project, planned, designed and built entirely by the Bhutanese engineers and local contractors without any external technical assistance. The project is supplying power to about 200 households in Gangjur geog, villages in and around Kellungchu valley. The power supply line from this project will be extended to Dungkhar in the North.

In addition to the commissioning of the above-mentioned new projects, existing mini-hydro such as the Thimphu Mini hydro (360 kW), Gangjur (120 kW), Chumey (1500 kW), Gidakom (1250 kW), Wangdi (300 kW) and Chenari (750 kW) have been rehabilitated. Construction of Yonglachu/Khoma small hydro (1 MW) in Lhuntse and Panbang (200 kW) and upgrading of Tintibi Mini hydro in Zhemgang were not carried out, as the sites were found techno-economically non-feasible for development after a pre-construction study. Extension of the existing eastern grid (fed by Kurichu) was found more feasible for these places.

The 8FYP budget outlay for these two projects have been re-appropriated accordingly to construct Mongar-Lhuentse grid supply line in Lhuentse, to install a 40 kW diesel generator at Panbang, and carry out grid extension works at Tintibi, Zhemgang. In total, 3.570 MW of standby/captive diesel capacity was added in the system in various Dzongkhag headquarters to improve the reliability of electric supply and for emergency need. In conclusion, additional hydropower of 82.4 MW and 506 MU annual generation capacity has been achieved during the plan period, increasing installed hydropower capacity with around 24 per cent. Total installed capacity of the power system at the end of the 8FYP is 444 MW, including diesel-based capacity. Annual average energy generation capacity has been increased to 2,326 MU from 1,838 MU at the end of 7th Fiver Year Plan period.

The Power Transmission Grid Programme

Under this Programme funded by the Government of India, the Eastern Transmission Grid has been constructed to evacuate and distribute Kurichu power. A 132 kV grid power line has been extended (67 km) from Kurichu to Nanglam (initially built for the Dungsam Cement Project power supply) via Nangkor in Pemagatshel under the scope of the Kurichu project. Similarly, a 132 kV line has been installed of (10 km) from Gyelposhing (Kurichu) to Killikhar (Mongar), and a 30 km long line was drawn from Killikhar to Kanglung (Trashigang). 24 kilometres of grid supply has been added from Nangkhor (Pemagatshel) to Deothang for power supply to Samdrupjongkhar. A 132 kV transmission line has been extended (131 km) from Nanglam via Tintibi, Zhemngang, to Gelephu, Sarpang, for export of surplus power generated by the Kurichu project, and to increase the reliability of power supply to the proposed Dungsam project in Nanglam. A total distance of 262 km, 132 kV line has been completed during the 8FYP with 6 major transmission substations for distribution of electricity to the load centres. The 48 km transmission line to Lhuentse substation at Tangmachu will be completed in the beginning of the 9FYP period.

In Western Bhutan, 23 km's of 66 kV transmission line has been completed from Lobessa to Basochu Upper Stage. Construction of 220 kV line from Semtokha to Basochu Lower Stage power plant has started. Similarly, construction has started of 400 kV lines to export Tala power and the 400/220 kV, 200 MVA interconnecting substation between Chukha and Tala grid supply at Malbasse, Pasakha, and will be completed during the 9 FYP. Survey works for drawing grid power supply lines to Tsirang and Dagana have also begun.

Under the improvement and upgrading of the transmission system, Gedu substation has been upgraded to 26 MVA, 66/33/11 kV voltage level for supply of construction power to the Tala project, and work is ongoing to upgrade the Singhegaon 220/66 kV substation by additional 50 MVA, Phuentsholing by 10 MVA, and Penden by 5 MVA.

The Power Distribution Programme

Under the Power Distribution Programme, 6,211 additional consumers (as of December 2000) have been added to the system. Extensive rural electrification has been carried out in about 189 villages in the Dzongkhags of Ha, Samdrupjongkhar, Trashingang, Trashiyangtse, Chukha, Thimphu, Punakha, Wangdu, Paro, and Lhuentse. 80 per cent of the work has been completed for rural electrification of additional 6,028 households in various Dzongkhags under the Asian Development Bank's loan project, Rural Electrification, Phase II.

Work has started to electrify other 388 households in Dungkhar, Chungkha and Zhemgang under the Sustainable Development Project funded by the Netherlands. Khuruthang Township was electrified and substantial works on improvement and upgrading of existing electric services in Thimphu and Paro have begun. About 253 km length of 33 and 11 kV overhead lines and 248 km long low voltage overhead lines (400/230 volts) were added to the distribution network during the first three years of the 8FYP period. The feasibility study, conducted during the 8FYP rural electrification survey, found the capacity coupling system non-feasible for rural electrification in Kengkhar village, Mongar. The commissioning of the Kurichu hydropower project has increased power sector activities in eastern Bhutan.

To cope with increased workload due to extensive rural electrification, the Department of Power established independent Electricity Supply Offices at Lhuentse, Mongar, Pemagatshel and Trashiyangtse in 2001. Earlier, electric services in these Dzongkhags were looked after from Trashigang. For the first time, grid electricity was made available to Yangtse Dzongkhag during the 8FYP.

The Alternate Energy Programme

For institutional lighting of lhakhangs, goenpas, chamkhangs, monastic schools/shedras, boarding schools, community schools and rural households, 180 sets of photovoltaic panels were installed in Chukha, Paro, Haa, Thimphu, Punakha, Pemagatshel, Yangtse, Bumthang, Samdrupjongkhar, Wangdue, Lhuntse, Trongsa and Mongar from the 7th Five Year Plan spill-over stock. In Gasa, additional 115 sets were installed by the Dzongkhag administration under donor assistance.

A National Strategy for Improved Stoves and Alternate Energy Technologies/Sources was also formulated. The Department of Forestry Services installed electric stoves in the Royal Bhutan Police complex as a pilot demonstration project for replacement/reduction of firewood use by other alternate energy sources. 1,350 solar electrification sets have been procured during the end of the 8FYP period, and their installation has started in various Dzongkhags for institutional lighting purpose.

Hydro meteorological networking and feasibility studies

Collection of hydro meteorological data for hydropower planning continued during the 8FYP. These data were collected from 21 river gauging stations and 84 meteorological stations, and are archived for future reference and record.

During the 8FYP, feasibility studies of Mangdechu Hydroelectric Project of 360 MW across Mangdechu in Trongsa Dzongkhag, and Punatsangchu Hydroelectric Projects of 870 MW across Punatsangchu in Wangduephodrang Dzongkhag were conducted. These two projects have been found techno-economically feasible and are planned for execution during the next Five Year Plan periods. Gathana micro-hydro in Gasa Dzongkhag was investigated and found unsuitable for electric supply to Gasa for techno-economic reasons.

Under the GEF/UNDP funded project "Study to remove barriers to micro hydro development in the Kingdom", four feasible micro-hydro sites have been identified at Sengor (Mongar), Sakten (Trashigang), Tang (Bumthang), and Gasa.

Institutional capacity building and technical assistance

The Asian Development Bank provided technical assistance for the development of legal and institutional frameworks for the power sector, major scope of which included the development of an Electricity Act, institutional framework for the power sector, and corporatization plans for utility functions of the Department of Power. Based on these studies and other plans, it is proposed to segregate and unbundled the present functions of the Department of Power into three functions: (1) Bhutan Electricity Authority (regulatory functions); (2) Bhutan Power Corporation (BPC) (utility functions); and (3) Department of Power/Energy (planning, policy and coordination functions). The study also proposed that all generating entities, such as Chukha, Kurichu, Basochu, and Tata, should belong to the same major holding company.

Tariff studies have suggested that future power tariffs shall be based on capacity, voltage level and energy consumption patterns for industrial, commercial and bulk consumers. Lifeline tariff rates based on various levels of consumption (slab system) are proposed for domestic consumers (both rural and urban). The long-range marginal costs of supply are reflected, and a cost-recovery system devised accordingly. Subsidies, if any, shall be as per this transparent tariff system.

A study for the preparation of water resources management plan and a hydropower master plan update funded by the Norwegian Government has just been launched and will be completed in the 9FYP period. Operations and maintenance Under this Programme, operations and maintenance of the existing power supply infrastructures were carried out including the capital cost involved in the purchase of power from Chukha Hydropower Corporation and import from India. Net plan budget expenditure by the end of 8FYP is estimated to be over Nu 3,216.397 million, which is 95 per cent of the 8FYP total sectoral budget outlay of Nu 3374 million on planned activities. This indicates sectoral achievement of over 90 per cent of the 8FYP target.

|
Energy Resources Section, Environment and Sustainable Development Division,
United Nations Economic and Social Commission for Asia and the Pacific